Project review meeting was held at CLPIU (Edu) on 10th November with contractors from all 7 districts. Contractors updated on the project progress and presented catch up plan to recover delays due to Covid19 & rainy season and complete the projects as per the contract period-May 2021.
Apart from project progress status, quality issues, procurement plan for MEP, Structural items, Hindrances & Solutions were also discussed.
The meeting was attended by representatives from CLPIU (Edu) & PMC. Mr Dilip Sekhar Shrestha, Dy. PD CLPIU presided over the meeting and emphasised for better coordination and efforts by the contractors & PMC for completion of the project as per timelines.