Daily Progress Report

Government of India Funded

Post-Earthquake Reconstruction of Education & Health Sector Projects in Nepal





Design & Project Management for Disaster Resilient Construction of 70 Schools and 1 Library


by

THE
PROJECT
THE
PROJECT
Reconstruction of
70 Schools in 8 Districts
Central Library at Tribhuvan University
Kathmandu
![]() |
---|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
STATUS
STATUS
Phase 1
All 08 Schools Handed Over
Phase 2
06/56 Schools Completed
Phase 3
06 Schools ongoing
Socio-Economic Impact
Employment Generation
(Constructions)
-
1.0 million man days
Employment Generation
(School Operation/yr)
-
700 Teachers
-
350 support staff
Skill Development
-
1000 engineers
-
5000 construction workers
Service to People
-
40000 students anually
-
1500 additional classrooms
Events Gallery

Ground Breaking Ceremony : School ID 71
Ground breaking ceremony for Kanti Bhirab Ma Vi (School ID 71) was held on 18-02-2021 at Thali, Kathmandu. Mr. Sushil Gyewali, CEO NRA was the chief guest and Ms. Namgya Khampa, DCM EoI was the special guest of the occasion.

Kick Off Meeting of Phase 3 Schools
Kick Off Meeting for the phase 3 schools was organised at CLPIU (Education) office at Gyaneswor, Kathmandu on 03-Jan-2021. It was attended by all the major stakeholders of the GOI funded schools reconstruction project : Embassy of India, CLPIU (Education), CSIR CBRI Roorkee, PMC Team and the
Appointed Contractor.

Inauguration of 3 Schools in Gorkha District
Mr. H V Shringla HE Foreign Secretary, Govt of India & Mr. Ramkrishna Sapkota, Secretary NRA jointly inaugurated 3 schools in Gorkha district on 27-11-2020 completed under India's post earthquake Reconstruction assistance.

Handing over of school at Nuwakot
Aiselubhume Secondary school in Nuwakot was handed over for service on 10th Feb 2020 in a colourful ceremony. It was the first school of the GoI funded reconstruction project. Former prime minister of Nepal Shri Pushpa Kamal Dahal was the chief guest of the ceremony.
Phase 1 hand over status
All the 8 schools - 5 schools in Nuwakot & 3 Schools in Gorkha have been formally handed over for service.
2 Schools have already completed Defect Liability Period.
Phase 2 schools update
Construction is on full swing at all 56 sites across 7 districts and will be available to hand over in the second half of the year.
Kavre Districts leads the way. As on date, 3 nos. schools in Kavre have completed construction and rest 07 schools are expected to finish by end of June 2021.
Phase 3 schools
Construction at Phase 3 school comprising of 4 schools in Kathmandu and 2 schools in Kavre districts have started. Mobilization commenced in the first week of Feb 2021 and is expected for completion by May 2022.
Tender Process by CLPIU,GoN
The Tender and Bidding Process for all projects have been completed except Tribhuvan University Central Library. This is expected to be completed soon.
Project Website Launched
Indian Ambassador to Nepal Mr. Vinay M Kwatra and CEO of National Reconstruction Authority, GoN Mr. Sushil Gyewali virtually launched the project information website on 22nd September 2020.