Progress Summary - Education

Project planning & progress is tracked on Microsoft Project Platform. Baseline schedule for all projects have been developed in the beginning of the project. The progress at all sites is reviewed and updated on a monthly basis.

Phase 1 -  Construction has already been completed for all the 8 schools - 5 in Nuwakot & 3 in Gorkha

Phase 2 & 3 - Construction is ongoing at 62 schools. Progress Summary is given below.

phase 2.png
District-wise Progress Summary for phase 2 schools till 30 Jun 2021
Click on the icons below to view progress of individual schools at various districts.
phase 3.png
District-wise Progress Summary for phase 3 schools till 30 Jun 2021
Click on the icons below to view progress of individual schools at various districts.