Design & Project Management for Disaster Resilient Construction of 70 Schools and 1 Library

by

THE
PROJECT
STATUS

Socio-Economic Impact

Central Library TU
Kanti Bhairab School KTM
3S9C block
3S13C block
3S6C block
LabLibrayEM block
Admin block
2S4C block
2S6C block
2S8C block
1S3C block
practical block
toillet block
Employment Generation
(Constructions)
  • 1.0 million man days
Employment Generation
(School Operation/yr)
  • 700 Teachers
  • 350 support staff
Skill Development
  • 1000 engineers
  • 5000 construction workers
Service to People
  • 40000 students anually
  • 1500 additional classrooms

Events Gallery

Ground Breaking Ceremony : School ID 71

Ground breaking ceremony for Kanti Bhirab Ma Vi (School ID 71) was held on 18-02-2021 at Thali, Kathmandu. Mr. Sushil Gyewali, CEO NRA was the chief guest and Ms. Namgya Khampa, DCM EoI was the special guest of the occasion.

Click here for more information.

Kick Off Meeting of Phase 3 Schools

Kick Off Meeting for the phase 3 schools was organised at CLPIU (Education) office at Gyaneswor, Kathmandu on 03-Jan-2021. It was attended by all the major stakeholders of the GOI funded schools reconstruction project : Embassy of India, CLPIU (Education), CSIR CBRI Roorkee, PMC Team and the 
Appointed Contractor.

Click here for more information.

Inauguration of 3 Schools in Gorkha District

Mr. H V Shringla HE Foreign Secretary, Govt of India & Mr. Ramkrishna Sapkota, Secretary NRA jointly inaugurated 3 schools in Gorkha district on 27-11-2020 completed under India's post earthquake Reconstruction assistance.

Handing over of school at Nuwakot

Aiselubhume Secondary school in Nuwakot was handed over for service on 10th Feb 2020 in a colourful ceremony. It was the first school of the GoI funded reconstruction project. Former prime minister of Nepal Shri Pushpa Kamal Dahal was the chief guest of the ceremony.

Phase 2 schools update

Construction ongoing at all sites 

Construction is on full swing at all 56 sites across 7 districts and will be available to hand over in the second half of the year. Project planning has been revised & catch up plans undertaken to recover delays due to Covid 19.

Phase 3 schools

Construction begins for 6 schools

Construction at Phase 3 school comprising of 4 schools in Kathmandu and 2 schools in Kavre districts have started. Mobilization commenced in the first week of Feb 2021 and is expected for completion by May 2022.

Phase 1 hand over status

4 schools handed over

3 schools in Gorkha and 1 school in Nuwakot has been officially handed over for service till date. Remaining 4 nos. schools are ready for handing over. 

Phase 1 construction

Construction completed at all 8 schools

Construction at 5 schools in Nuwakot & 3 schools in Gorkha districts have been completed and ready for handing over to the servce of people. The inauguration dates will be announce shortly. 1 school in Nuwakot has already been handed over and in service since Feb 2020.

Tender Process by CLPIU,GoN

Central Library TU & 6 schools

The Tender and Bidding Process is being carried-out by CLPIU(Education), Government of Nepal for 6 schools has been concluded and Tender for Central Library, Tribhuvan University is under review and likely to be completed soon.

Project Website Launched

For project related information

Indian Ambassador to Nepal Mr. Vinay M Kwatra and CEO of National Reconstruction Authority, GoN Mr. Sushil Gyewali virtually launched the project information website on 22nd September 2020.

  • Twitter
  • Facebook
  • YouTube

Showcase Projects

1/5
1/2

Website Development     |     Privacy Policy     |     Copyright Policy     |     Hyperlinking Policy     |     Accessibility Statement     |     Help

Site Managed By : IRCLASS Nepal 2020. All Rights Reserved. For more information please mail to cbrinepal@gmail.com

Visitors : 

Page last updated on : 16.11.2020

Bharat Nepal Maitri